SWG renovate district heating pipeline in the Schiffenberger Tal industrial estate

On 10 November, SWG will begin renovating a main district heating pipeline in Ferniestrasse.

Like all technical systems, district heating pipes are subject to an ageing process. This means that the well-insulated pipes sometimes need to be replaced. This is exactly what is now due to happen in Ferniestrasse. Over a total length of around 270 metres, Stadtwerke Gießen (SWG) will be laying a new pipe in a largely new route over the coming months.

Hardly any restrictions

The construction work is divided into two sections. Work will start on 10 November between the end of Ferniestraße and the junction with Ernst-Leitz-Straße. Fortunately, the disruption to traffic caused by the roadworks will be kept within manageable limits. Thanks to the lane width of eleven metres, vehicles can pass through the area as usual in both directions despite the closure of one lane. Both the furniture store located here and the police station will therefore remain accessible as usual.

An outlook

The plan is to complete the first construction phase by the end of 2025. Whether this will succeed depends on various factors. "Some of them - such as the weather conditions - are beyond our control. But we can assure all residents that we will complete the construction work as quickly as possible," explains Ulli Boos, company spokesperson for SWG.

SWG will begin with the second section in 2026 as soon as the expected weather conditions allow for normal construction progress. "In this way, our colleagues will ensure that the disruption to the local businesses is kept to a minimum," continues Ulli Boos. As things stand today, the second construction phase will require a partial closure of Ferniestrasse. The work should be fully completed by the end of November 2026.