22.06.2018

From 2 July, the district heating network of Stadtwerke Gießen (SWG) will be extended in Neuenweg. In order to lay the district heating pipes, a trench about 30 metres long will be opened up in the middle of the street. The area affected by this construction work between Seltersweg and Erlengasse is located in the pedestrian zone. From 2 July, there will be a full closure for delivery traffic from Johannesstraße. Pedestrians can use the street without restrictions as the trench is in the centre of the street. Unrestricted access to the houses is also guaranteed during the construction work. The construction work will take around four weeks and will be completed around 27 July, so that the pedestrian zone can be used again by delivery traffic for the city festival in mid-August.

Local residents will be informed directly by SWG in the next few days.